Pouring Concrete in Hot Weather: What BOM's Warmer Outlook Means for Your Summer Pour

8 October 2026

BOM's latest outlook makes warmer-than-average days and nights more likely across most of NSW through to December, so a summer driveway or slab pour needs planning around how fast water leaves the fresh concrete, especially on windy days, and a curing plan that starts straight away and runs at least 7 days.

If you're planning a driveway or slab in the Hunter before Christmas, BOM's outlook issued on 1 October is worth reading for its nights as much as its days. Minimum temperatures are "very likely (greater than 80% chance)" to be above average across almost all of Australia from October to December. For unusually high maximums, the highest chances (over 80%) include most of New South Wales.

In hot weather the main danger to a fresh slab is water leaving it too fast, and wind speeds that up as much as heat does. So the practical answer for a summer pour is twofold. Plan the pour around the day's conditions. Then cure it properly for at least a week.

These are odds, not a forecast. Here at Concreters Near Me, that is how we'd read them: as a reason to plan, not a reason to panic.

What BOM's 1 October outlook says for Australia and NSW

BOM's seasonal outlook: chance of above-average temperatures, October to December Three horizontal bars, each drawn to the lower bound of its range. Minimum temperatures above average, almost all of Australia: greater than 80% chance. Maximum temperatures above average, most of Australia: 60% to over 80% chance. Unusually high maximums, much of the southern two-thirds: greater than 50% chance. A separate callout for warm nights: unusually high minimums across much of the country, more than 4 times the normal likelihood. Chance of above-average temperatures, October to December Minimum temperatures above average Almost all of Australia: greater than 80% chance Maximum temperatures above average Most of Australia: 60% to over 80% chance Unusually high maximums Much of the southern two-thirds: greater than 50% chance 0% 100% Warm nights Unusually high minimums, much of the country: more than 4 times the normal likelihood
BOM's seasonal outlook: chance of above-average temperatures, October to December Three horizontal bars, each drawn to the lower bound of its range. Minimum temperatures above average, almost all of Australia: greater than 80% chance. Maximum temperatures above average, most of Australia: 60% to over 80% chance. Unusually high maximums, much of the southern two-thirds: greater than 50% chance. A separate callout for warm nights: unusually high minimums across much of the country, more than 4 times the normal likelihood. Chance of above-average temperatures, October to December Minimum temperatures above average Almost all of Australia: greater than 80% chance Maximum temperatures above average Most of Australia: 60% to over 80% chance Unusually high maximums Much of the southern two-thirds: greater than 50% chance 0% 100% Warm nights Unusually high minimums, much of the country: more than 4 times the normal likelihood
Odds, not a forecast. BOM outlook issued 1 October 2026.

Source: Bureau of Meteorology

The headline is warmth, day and night. BOM says daytime temperatures are likely to be above average for most of Australia, and overnight temperatures are likely to be above average across Australia. For warm nights, the chance of unusually high minimums is "more than 4 times the normal likelihood" across much of the country.

Days lean the same way. Maximum temperatures are likely (60% to over 80% chance) to be above average across most of Australia, with a greater than 50% chance of unusually high maximums across much of the southern two-thirds.

Rain is less settled. Much of eastern Australia has "roughly equal chances of above or below average" rainfall, and the wet signal in the east "emerges later in the outlook period".

BOM also says El Niño is at near-record levels and likely to peak in late spring or summer as a very strong event, while warning that a strong El Niño "does not necessarily mean strong impacts" on Australia.

A strong El Niño "does not necessarily mean strong impacts" on Australia.

Bureau of Meteorology

A very strong El Niño does not guarantee a hot, dry summer: BOM's El Niño explainer, updated 17 September, says "no 2 events are the same" and "it's too early to say what summer will be like". BOM also notes that El Niño's influence on rainfall typically reduces around early summer.

What September already showed in NSW and the Hunter

What September showed
MeasureSeptember 2026
Australia, temperatureSecond-warmest September on record, +2.71 °C above average
NSW, rainfall80% below average, 7.1 mm
NSW, mean maximum+4.41 °C above average
Williamtown RAAF32.8 °C on 5 September, an early-season record for the station
Williamtown RAAF35.4 °C on 21 September, an early-season record for the station
Observed records, not forecasts.

Source: Bureau of Meteorology

The season has form. September 2026 was Australia's second-warmest September on record, at +2.71 °C above the 1961 to 1990 average. NSW had its second-warmest and fourth-driest September on record, with rainfall 80% below average, at 7.1 mm, and a mean maximum anomaly of +4.41 °C, the 3rd highest.

Closer to home, Williamtown RAAF recorded 32.8 °C on 5 September and 35.4 °C on 21 September. Both were early-season maximum temperature records for that station.

Those are things that already happened. They are not a forecast for your street in December. They do show that hot pour days can arrive well before summer officially starts.

Pouring concrete in hot weather: what heat and wind do to a fresh slab

Evaporation from a fresh slab in still air and in a 15 km/h breeze Two freshly placed slabs inside timber formwork on a damp sub-grade, each under the sun. Left, still air at 0 km/h: two small arrows show water evaporating from the surface. Right, a breeze of 15 km/h: wind streaks cross the slab and eight arrows show four times the evaporation. Still air, 0 km/h Damp sub-grade Fresh slab Timber formwork Arrows: water evaporating from the surface A breeze of 15 km/h Damp sub-grade Fresh slab Timber formwork Wind Arrows: water evaporating from the surface
Evaporation from a fresh slab in still air and in a 15 km/h breeze Two freshly placed slabs inside timber formwork on a damp sub-grade, each under the sun. Left, still air at 0 km/h: two small arrows show water evaporating from the surface. Right, a breeze of 15 km/h: wind streaks cross the slab and eight arrows show four times the evaporation. Still air, 0 km/h Damp sub-grade Fresh slab Timber formwork Arrows: water evaporating from the surface A breeze of 15 km/h Damp sub-grade Fresh slab Timber formwork Wind Arrows: water evaporating from the surface
Evaporation rises to four times when wind goes from 0 to 15 km/h on a hot day.

Source: Holcim Australia

Concrete needs its water to gain strength. Holcim names the main hot-weather problems as early water loss and early setting through too-rapid drying. Left unplanned, those can show up as reduced strength, crazing or cracking, shrinkage cracks and finishing difficulties.

Wind is the part people underrate. Holcim says evaporation from fresh concrete "will increase to four times when wind velocity rises from zero to only 15km per hour on a hot day". Fifteen kilometres an hour is a breeze you'd barely notice on a walk. On a fresh slab it is a drying machine.

A thermometer pushed into fresh concrete, marked 35°C A thermometer pushed into a fresh slab, its bulb in the concrete rather than in the air, marked 35°C. Label: the maximum concrete temperature for field placing under AS1379. Second label: this is the concrete's temperature, not the air's. Air Fresh concrete 35°C 35°C: the maximum concrete temperature for field placing under AS1379 This is the concrete's temperature, not the air's.
A thermometer pushed into fresh concrete, marked 35°C A thermometer pushed into a fresh slab, its bulb in the concrete rather than in the air, marked 35°C. Label: the maximum concrete temperature for field placing under AS1379. Second label: this is the concrete's temperature, not the air's. Air Fresh concrete 35°C 35°C: the maximum concrete temperature for field placing under AS1379 This is the concrete's temperature, not the air's.
The 35°C limit is read in the concrete, not the air.

Source: Holcim Australia

You may hear 35°C mentioned. Holcim notes that 35°C is the maximum concrete temperature for field placing allowed under AS1379. That is the temperature of the concrete itself. It is not an air temperature for calling a pour off, so a forecast top of 35 is not, on its own, a yes or a no.

How fast is too fast: the evaporation rates that signal trouble

Evaporation rate from fresh concrete, kg/m² per hour A horizontal scale from 0 to 1.1 kg/m² per hour. From 0.5 the scale is shaded and labelled: plastic cracking trouble potentially in the making. From 1.0 it is shaded darker and labelled: precautions almost mandatory. A marker at 1.1 shows Holcim's worked example: air 25°C, humidity 40%, concrete 25°C, wind 20 km/h. Evaporation from fresh concrete (kg/m² per hour) Above 1.0: precautions almost mandatory Above 0.5: plastic cracking trouble potentially in the making 0 0.5 1.0 1.1 1.1: Holcim worked example air 25°C, humidity 40%, concrete 25°C, wind 20 km/h
Evaporation rate from fresh concrete, kg/m² per hour A horizontal scale from 0 to 1.1 kg/m² per hour. From 0.5 the scale is shaded and labelled: plastic cracking trouble potentially in the making. From 1.0 it is shaded darker and labelled: precautions almost mandatory. A marker at 1.1 shows Holcim's worked example: air 25°C, humidity 40%, concrete 25°C, wind 20 km/h. Evaporation from fresh concrete (kg/m² per hour) 0 0.5 1.0 1.1 Above 0.5: plastic cracking trouble potentially in the making Above 1.0: precautions almost mandatory 1.1: Holcim worked example air 25°C, humidity 40%, concrete 25°C, wind 20 km/h

Source: Holcim Australia

Evaporation from fresh concrete is measured in kilograms of water per square metre per hour. Holcim puts the warning lines here: plastic cracking trouble is "potentially in the making" above 0.5 kg/m² per hour, and precautions are "almost mandatory" above 1.0 kg/m² per hour.

The worked example is the eye-opener. Air at 25°C, humidity at 40%, concrete at 25°C and wind at 20 km/h gives 1.1 kg/m² per hour. That is past the "almost mandatory" line on a day most of us would call pleasant. The breeze, not the heat, is what pushed that example over the line.

What to ask your concreter before a summer pour

Before a summer pour, ask about

Source: Holcim Australia

You don't need to run the numbers yourself. You do want to know there is a plan. These are questions worth raising, drawn from Holcim's hot-weather precautions.

Timing. What time will the pour start? In extreme heat, Holcim suggests it may be wise to start in the afternoon, so the work runs into the cooler evening.

The ground. Will the sub-grade and forms be moistened first? Holcim wants the sub-grade "damp, but not muddy", so dry ground doesn't draw water out from underneath.

The order. Is the delivery sized to the crew and the day? Holcim's advice is to avoid delay in placing, and don't order more than can be finished and covered.

Shade. Will the concrete be shaded, with wet coverings until finishing?

Workability. Adding water on site to keep concrete workable in heat is not a harmless fix, because excess water lowers strength, raises shrinkage and cracking, and can cause dusting and scaling. Holcim says better workability and longer setting times are best achieved with chemical admixtures specified by AS 1478, which mostly must be added at the plant. That makes it a conversation for before the truck is booked, not on the day.

Curing. When does curing start, and how long does it run? The short answer you are listening for is "straight away" and "at least 7 days", which the next section covers.

How to cure concrete in hot weather

Curing a slab in hot weather, from pour day through the first week A timeline from pour day to day 7. Pour day: start curing as soon as possible. Through the first week, a continuous band: keep curing for at least 7 days. A callout: ideal curing temperature 23°C, meaning the concrete's own temperature. At the end of the timeline: properly cured concrete is 80 to 100% stronger than concrete not cured at all. Ideal curing temperature: 23°C (the concrete's own) Pour day Start curing as soon as possible Day 7 Keep curing for at least 7 days Through the first week Properly cured concrete is 80 to 100% stronger than concrete not cured at all
Curing a slab in hot weather, from pour day through the first week A timeline from pour day to day 7. Pour day: start curing as soon as possible. Through the first week, a continuous band: keep curing for at least 7 days. A callout: ideal curing temperature 23°C, meaning the concrete's own temperature. At the end of the timeline: properly cured concrete is 80 to 100% stronger than concrete not cured at all. Ideal curing temperature: 23°C the concrete's own temperature Pour day Start curing as soon as possible Through the first week Keep curing for at least 7 days Day 7 Properly cured concrete is 80 to 100% stronger than concrete not cured at all

Source: Holcim Australia

Curing is where summer slabs are won or lost. Holcim says to start curing as soon as possible and to cure for at least 7 days. The ideal curing temperature is 23°C, and Holcim means the concrete's own temperature, which is why shade and cover matter on a hot day.

Here is why it matters. If concrete dries out in hot weather, hydration "stops right at the point where the concrete loses its moisture". And properly cured concrete is 80 to 100% stronger than concrete not cured at all. Holcim adds that properly cured surfaces wear well and crack less from drying shrinkage.

Curing methods and what to watch in summer
Curing methodWhat to watch
Wet hessian or sandKeep it constantly damp, because wetting and drying in turns can cause cracking.
Plastic sheetingA listed curing method that can double as storm cover.
Ponding or mistingA listed curing method.
Membrane compoundWhite compounds reflect sun and cut surface temperature, and it must suit any finish you intend to apply later.

Source: Holcim Australia

Holcim lists the options: wet hessian or sand, plastic sheeting, ponding or misting, or a membrane compound. Each has a catch in summer.

One more caution: Holcim says to avoid big temperature differences between the concrete and its curing environment, to prevent thermal shock cracking. Steady beats dramatic.

For what happens after the first week, including when you can walk or drive on the slab, see how long concrete takes to cure.

Heat and storms in the same season

One fresh slab shown twice: in hot morning sun, then under a late-afternoon storm Left: a fresh slab beside a house in hot morning sun. Right: the same slab under a dark late-afternoon storm cloud with rain, covered by plastic sheeting held along its edges by timber. Morning: hot sun Fresh slab Late afternoon: storm Plastic sheeting
One fresh slab shown twice: in hot morning sun, then under a late-afternoon storm Left: a fresh slab beside a house in hot morning sun. Right: the same slab under a dark late-afternoon storm cloud with rain, covered by plastic sheeting held along its edges by timber. Morning: hot sun Fresh slab Late afternoon: storm Plastic sheeting
Have cover on site before the surface has firmed up.

A summer pour can face a hot morning and a downpour by late afternoon. BOM notes that warmer seas, forecast mainly to Australia's west, can enhance atmospheric moisture, "increasing potential for high intensity rainfall", and its wet signal for the east "emerges later in the outlook period". Its El Niño explainer adds that a warming climate increases the likelihood of hotter conditions, heatwaves, fire weather and heavy rainfall.

So add one more question to your list: what cover is on site if a storm rolls in before the surface has firmed up? Plastic sheeting is already one of Holcim's curing methods, so it is worth asking whether it will be on site anyway.

Our piece on what drives the cost of a concrete driveway explains where curing and timing fit.

Can you stop concrete cracking in hot weather?

Five steps that all work on keeping water in the concrete Keeping water in the concrete sits at the centre. Five steps point to it: damp sub-grade; shade; a sensible order size; no water added on site; curing that starts at once and keeps going. Keeping water in the concrete Damp sub-grade Shade A sensible order size No water added on site Curing that starts at once and keeps going
Five steps that all work on keeping water in the concrete Keeping water in the concrete sits at the centre. Five steps point to it: damp sub-grade; shade; a sensible order size; no water added on site; curing that starts at once and keeps going. Damp sub-grade Shade A sensible order size No water added on site Curing that starts at once and keeps going Keeping water in the concrete

Source: Holcim Australia

Honestly, no precaution removes the risk. What the steps above do is shift the odds. A damp sub-grade, shade, a sensible order size, no water added on site, and curing that starts at once and runs at least 7 days all work on the same problem: keeping water in the concrete long enough for it to gain strength.

The season's odds favour warmth. The slab's needs don't change. Plan for the conditions on the day, not the average.

Planning a summer pour with Concreters Near Me

Concreters Near Me covers concreting across Newcastle, Lake Macquarie and the Hunter, from driveways and pathways to shed and garage slabs and pool surrounds.

If a pour is on your list for the warmer months, your next step is simple. Tell us what you're planning and roughly when through our contact page, and bring the questions above to the conversation.

Sources

Have a project in mind?

Get a free quote from your local concreters

Driveways, pathways, slabs, resurfacing and more across Newcastle and the Hunter.

Get a Free Quote